Required Documents for DM:
Required Drawings for DM:
Dubai Municipality Self Decor:
Required Forms for Dubai Municipality Approval:
1. Contrctor Change Form.
2. Contrcator changing before issuing the permit.
3. Changing contractor with agreement[Arabic].
4. Changing contractor without agreement[Arabic].
5. Changing contractor owner undertaking[Arabic].
6. DMBLDP3F1.
7. DMBLDP3F2.
8. DMBLDP3F3.
9. DMBLDP3F4.
10. DMBLDP3F5.
11. DMBLDP3F6.
12. DMBLDP3F7.
13. DMBLDP3F8.
14. DMBLDP3F9.
15. DMBLDP3F10.
16. DMBLDP3F11.
Required Forms for Trakhees Approval:
1. CMF-F01a, Application form for Modification NOC - OFFICE AND RETAIL, Rev.
2. CMF-F01b, Application form for Modification NOC - INDUSTRIAL, Rev.
3. CMF-F01c, Application form for Modification NOC - LANDLORD UNIT, Rev.
4. CMF-F01e, Application form for Modification NOC - VACATING PREMISES, Rev.
5. CMF-F01f, Application form for Revalidaiton of Cancellation of Modification.
6. CMF-F01g, Application form for Amendment of Modification NOC, Rev.
7. CMF-F02a Application form for MCC Rev 00 Dec17.
8. CMF-F02b Undertaking Letter FORMAT- for incomplete works-Rev. 00- Dec1.
9. COC-Modification Works Undertaking Letter Template.
10. COC-MW-Complaince Form.
11. CSF-01a COC 1 Compliance Form Rev 4 Dec 2017.
12. CSF-04a COC MW Compliance Form Rev 4 Dec 2017.
13. CSF-06a COC Demolition Compliance Form Rev 2 Dec 2017.
14. CHANGE OF CONSULTANT.
Required Documents for DDA Fit-out Permit:
1.Fit-out Permit Request Form (General Work) (In case of applying through customer service center))
2.Contractor Appointment Letter by Tenant
3.Copy of EJARI
4.NOC from Building Owner
5.NOC from relevant Authority
6.Existing and proposed drawings (as per Circular no. 229)
Note:
*Dubai Civil Defence Completion Certificate is required prior to obtaining Fit-Out Completion Certificate
*For coring less than 200mm, there should be no impact on any Structural elements such as tendons and should be atleast 1m far from the column
*For adding Structural Elements, Changing the Use or Additional GFA, Requestor to submit for Design Modification Approval request
*If DDA reviewed the submission and found out that it should be Design Modification , then there will be no refund of Fit-Out General fees
*NOC from the main contractor, main consultant and plot owner is required if the building did not obtained a completion certificate yet
Fees
*Normal submission: AED 0.90 per ft2 (minimum AED 200) (Maximum AED 10,000)
*Fast track submission: AED 5,000 + normal submission fees
*An additional fees of AED 10 as “Knowledge Dirham” and AED 10 as “Innovation Dirham” is applicable per transaction.
Duration
*Normal Submission: 3 working days
*Fast track submission: 2 working days
Required Documents for DDA Fit-out Completion Certificate:
1. Fit-out Completion Certificate Request Form (In case of applying through customer service center).
General Fit-out Completion:
2. NOC from tenant to issue the Completion.
3. Tenant license for the unit.
4. Dubai Civil Defence Completion Certificate.
Minor Fit-out Completion:
2. NOC from tenant to issue the Completion.
3. Tenant license for the unit.
Fees
* Not applicable
Duration
* 3 working days
Required Documents for DDA Night Shift Work Permit:
1. Night Shift Work Permit Request Form (In case of applying through customer service center).
2. NOC from consultant.
Fees
* Not applicable
Duration
* 3 working days
Required Documents for DDA Consultant/Contractor Replacement:
* Consultant/Contractor Replacement Application Form (In case of applying through customer service center).
Consultant Replacement
* New Consultant Appointment Letter by the owner (In case of applying online)
* Undertaking letter by Consultant
Contractor Replacement
* NOC from old contractor (In case of applying online)
* Appointment and Acceptance Letter to be signed and stamped by owner, consultant and new contractor (In case of applying online)
Consultant and Contractor Replacement
* Appointment and Acceptance Letter to be signed and stamped by owner, consultant and new contractor (In case of applying online)
* Undertaking letter by Consultant
* NOC from old consultant and contractor (In case of applying online)
Note: Replacing Contractor requested to apply for Re-Demarcation Certificate (if applicable)
Fees
* Request with NOC from the previous Contractor/ Consultant: AED 500
* Request with undertaking letter from the Owner: AED 2,000
* An additional fees of AED 10 as “Knowledge Dirham” and AED 10 as “Innovation Dirham” is applicable per transaction.
Duration
* Process Duration of Consultant and Contractor Replacement:2 working days
* Process Duration of Consultant Replacement: 2 working days
* Process Duration of Contractor Replacement: 2 working days
Required Documents for DEWA:
1. Copy of DEWA approved TCL/MD, MDBs/SMDBs etc... schedule (Main project).
2. Load distribution schedules of distribution boards. .
3. Wiring Layouts – Lighting.
4. Wiring Layouts – Power .
5. Landlord NOC ( In DEWA prescribed format).
6. Tenancy Contract + Trade License + Passport Copy.
Dubai Authority Approval refers to the official permission or clearance required from government entities in Dubai before starting, modifying, or operating any business, construction, or renovation project.
Why It’s Needed
To ensure:
Public safety
Regulatory compliance
Fire and health standards
Proper use of property or land
It applies to everything from interior fit-outs and structural changes to opening a new business or clinic.
When Do You Need It?
You typically need authority approvals when:
Opening a new business or branch
Doing interior fit-outs for offices, salons, shops, or restaurants
Modifying a villa, warehouse, or commercial space
Installing a mezzanine or partitions
Meeting fire, health, or zoning regulations
Common Authorities in Dubai
Authority |
Role |
Dubai Municipality (DM) |
Building permits, fit-out layouts, hygiene standards |
Dubai Civil Defense (DCD) |
Fire safety approvals and inspections Dubai Development Authority (DDA) - Building Permit, Fitout permit |
Dubai Economic Department (DED) |
Business licenses and activity approvals |
Trakhees |
Free zone and industrial approvals (JAFZA, DTCM) |
DEWA, TECOM, RTA, DHA |
Utilities, telecom, transport, health-specific projects |
Key Takeaway
Without proper approvals, your project can be delayed, fined, or even shut down. It’s essential to work with a licensed consultant who understands Dubai's regulatory landscape.
Here's a clear step-by-step guide on how to get Dubai Municipality (DM) approval for your construction, fit-out, or renovation project:
How to Get Dubai Municipality Approval
Dubai Municipality is one of the key government bodies that regulates building permits, layout approvals, hygiene standards, and modifications to residential and commercial properties.
1. Identify the Type of Work
You’ll need DM approval if you are:
Building or modifying a villa, office, shop, warehouse, etc.
Doing interior fit-outs (salons, restaurants, clinics, etc.)
Installing partitions, mezzanine floors, HVAC systems, etc.
2. Hire a DM-Registered Consultant/Contractor
You must work with a Dubai Municipality-approved engineering or architectural consultant to:
Prepare technical drawings
Ensure your design complies with DM codes and regulations
Submit applications on your behalf via the DM e-Services Portal Dubai BPS
3. Prepare and Submit Required Documents
Typical documents & drawings include:
Proposed layout drawings (architectural, structural, MEP)
Trade license and tenancy contract (Ejari)
Building completion certificate (for existing buildings)
Structural calculations (if needed)
NOC from building owner/landlord
Fire and safety plans (
4. Submit via Dubai Municipality e-Services
Your consultant logs into: https://www.dm.gov.ae
Uploads all drawings and documents
Chooses the relevant permit type (Fit-out Permit, Building Permit, etc.)
5. Review, Feedback & Revisions
Dubai Municipality reviews the submission
They may request corrections or additional documents
Consultant resubmits revised plans if needed
6. Receive Approval / Permit
Once approved, you’ll receive:
Building Permit (for construction/modification)
Or a Fit-Out Permit (for interior work)
This is valid for a specific period (usually 6 months–1 year)
7. Final Inspections
DM inspection and completion certificate is mandatory before occupying the space . Periodical structural inspection is required before casting concrete, else will end up in violation and fines
Pro Tip:
Use DM-accredited contractors and consultants to avoid delays.
Make sure all materials and systems comply with Dubai Building Codes and Green Building Regulations.
Here's a clear breakdown of the typical costs associated with authority approvals in Dubai, keeping in mind that prices may vary based on project size, type, and location (mainland or free zone):
$ Cost of Authority Approvals in Dubai (Estimated 2024)
1. Dubai Municipality (DM) Approvals
Type of Work |
Estimated Cost |
Interior Fit-Out Permit (Retail/Office) |
AED 1,000 – AED 5,000 |
New Building Permit |
AED 10,000 – AED 100,000+ |
Drawing Approval Fees |
AED 1 – AED 3 per sq. meter |
Site Inspection Fee |
AED 500 – AED 2,000 |
2. Dubai Civil Defense (DCD) Approvals
Scope |
Estimated Cost |
Fire Safety Design NOC |
AED 1,000 – AED 2,500 |
Final Fire Inspection |
AED 500 – AED 2,000 |
Emergency Lighting System Design Review |
AED 750 – AED 1,500 |
3. Dubai Health Authority (DHA) – Clinics/Medical Centers
Approval Type |
Estimated Cost |
Initial Facility Licensing |
AED 5,000 – AED 7,000 |
Final Licensing Inspection |
AED 2,000 – AED 3,000 |
4. Trakhees Approvals (JAFZA, Nakheel, etc.)
Approval Type |
Estimated Cost |
Fit-Out Permit |
AED 2,000 – AED 10,000+ |
Structural/Mezzanine Approvals |
AED 5,000 – AED 15,000+ |
Fire NOC (Trakhees – EHS) |
AED 1,000 – AED 2,500 |
5. Dubai Economic Department (DED)
Scope |
Estimated Cost |
Initial Approval & Trade Name |
AED 620 – AED 1,000 |
Professional / Commercial License |
AED 8,000 – AED 15,000+ |
6. Other Potential Costs
Consultant Fees (Design & Submission): AED 3,000 – AED 20,000+
Contractor Mobilization/NOC Fees: AED 1,500 – AED 5,000
Mall Management Approval (if applicable): AED 1,000 – AED 10,000
???? Notes:
Fees vary depending on area (Mainland, Free Zone), project complexity, and built-up area.
In Free Zones, fees are separate and governed by the zone’s internal authority.
Urgent approvals or fast-track submissions may incur additional charges.
Here’s a simplified guide to the authority approvals required for setting up a business in Dubai, depending on the business type, activity, and location (mainland or free zone):
Authority Approvals Required for Business Setup in Dubai
Starting a business in Dubai involves obtaining several government and regulatory approvals to ensure your operations meet all legal, safety, and zoning standards.
1. Department of Economic Development (DED) – For Mainland Businesses
Trade Name Reservation
Initial Approval Certificate
Activity-specific NOCs
Business License Issuance
(e.g., Professional, Commercial, Industrial)
Main Approval Body for Mainland Businesses
2. Free Zone Authorities – For Free Zone Businesses
Each Free Zone has its own governing body, such as:
Dubai Multi Commodities Centre (DMCC)
Dubai Silicon Oasis (DSO)
Dubai Airport Free Zone (DAFZA)
Dubai Development Authority (DDA)
♦ These zones combine licensing and property management, often streamlining the approval process.
3. Dubai Municipality (DM)
Required for:
Interior Fit-Out Works (office, shop, clinic)
Construction or Renovation Approvals
Health & Safety Compliance
Food & Beauty-related businesses
♦ DM approval is mandatory for physical modifications or fit-outs.
4. Dubai Civil Defense (DCD)
Required for:
Fire & life safety system approvals (offices, warehouses, salons, restaurants)
Fit-out permits involving fire-rated materials, sprinklers, alarms
♦ Essential for any public-access or commercial property.
5. Dubai Health Authority (DHA)
Needed if your business is:
Clinic / Medical Center
Dental / Cosmetic Surgery
Diagnostic Labs
Health Consultation Services
♦ DHA ensures all health-related facilities meet medical licensing and hygiene standards.
6. Trakhees / EHS (Ports & Customs Authority)
Applicable to businesses in:
JAFZA
Palm Jumeirah
International City
Dragon Mart Area
♦ Covers planning, civil, and fire safety approvals for free zone projects.
7. Food Safety Department
Part of DM or Trakhees (depending on jurisdiction), required for:
Restaurants, Cafés, Food Kiosks
Catering, Central Kitchens
♦ Approves kitchen design, hygiene plan, storage layout.
8. Public Health & Safety Department
Required for:
Salons & Spas
Gyms & Wellness Centers
Childcare or Elderly Care Facilities
♦ Inspects equipment, sterilization, ventilation, and cleanliness.
► Final Checklist of Common Approvals:
Approval |
Required For |
DED / Free Zone License |
All businesses |
Dubai Municipality (DM) |
Any physical location or fit-out |
Civil Defense (DCD) |
Fire safety compliance |
DHA |
Medical businesses |
Food Safety Dept. |
Restaurants, cafés, food-related services |
Trakhees / EHS |
Free zones under PCFC |
Health & Safety |
Salons, spas, clinics, gyms |
The time required for Dubai authority approvals depends on the type of project, the specific authority, and whether all documents are correctly submitted.
► Typical Timeframes by Approval Type
Approval Type |
Estimated Time |
Dubai Municipality (DM) – Fit-out Permit |
3 – 10 working days |
Dubai Municipality – Building Permit |
10 – 20 working days |
Dubai Civil Defense Approval |
5 – 10 working days |
DED Initial Approval / Trade Name Reservation |
1 – 2 working days |
Trakhees Approval (Free Zones) |
7 – 15 working days |
Fire Safety Design Approval (Civil Defense) |
7 – 14 working days |
Completion Certificate (Post Construction) |
5 – 10 working days |
» What Can Affect the Timeline?
Incomplete or incorrect drawings/documents
Using non-registered consultants or contractors
Site inspections or resubmission requirements
Working in free zones with additional regulations
Backlogs at government departments
♦ Pro Tips to Speed Up Approval
Work with an experienced approval consultant
Ensure your drawings follow DM & DCD standards
Submit all documents at once and in the correct format
Follow up regularly via the e-services portal
Here’s a clear and complete guide to the Dubai fit-out approval process—essential if you’re planning to renovate or customize a commercial space like an office, shop, salon, restaurant, clinic, or warehouse.
️ Dubai Fit-Out Approval Process
Fit-out approval is mandatory to ensure your interior modifications are safe, legal, and aligned with Dubai Municipality and Civil Defense standards.
1. Appoint a DM-Approved Consultant or Contractor
You must work with a Dubai Municipality-registered consultant to:
Prepare the architectural, structural, and MEP drawings
Submit applications on your behalf
Ensure design complies with Dubai Building Code and fire safety standards
2. Gather Required Documents
Typical submission includes:
Trade License & Ejari (tenancy contract)
NOC from landlord/building management
Proposed layout (AutoCAD format)
Fire safety layout (for DCD)
Structural calculations (if structural work involved)
Material specifications (especially for fire-rated materials)
3. Submit Drawings via e-Services
Consultant submits documents on:
Dubai Municipality (DM) Portal → for architectural and civil approvals
Dubai Civil Defense Portal (DCD) → for fire safety approvals
Trakhees Portal → if the site is in a free zone like JAFZA, DAFZA, etc.
4. Fire & Safety Review (Civil Defense)
If applicable (e.g., restaurant, clinic, warehouse):
Civil Defense reviews fire exits, alarms, sprinklers, extinguishers, etc.
Fire-fighting layout must be prepared by certified contractors
5. Revisions / Resubmission (if required)
Authorities may request updates or corrections
Consultant resubmits revised plans
6. Permit Issued
Once approved, you’ll receive the Fit-Out Permit that allows construction or renovation to begin.
7. Site Inspection (if applicable)
For high-risk projects, DM or DCD may inspect the site
Ensure all works are executed as per approved plan
8. Completion Certificate / Final NOC
After finishing the fit-out, submit:
As-built drawings
Completion photos
Request for final inspection or Completion Certificate
► Authorities Involved
Dubai Municipality (DM) – Layout and structural approval
Dubai Civil Defense (DCD) – Fire and safety compliance
DED or Free Zone Authority – License link and approvals
DEWA / Trakhees / TECOM – For utilities and zone-specific rules
♦ Pro Tips:
Use fire-rated materials and follow Green Building Regulations
Plan early – approval can take 1 to 3 weeks
Fit-out without approval may result in fines or shutdown
Here’s a clear and complete guide on getting mezzanine floor approval in Dubai, whether for a warehouse, office, showroom, or industrial space:
Mezzanine Floor Approval in Dubai
A mezzanine floor is an intermediate floor built inside an existing building (usually a warehouse or commercial unit) to increase usable space. In Dubai, it requires strict approval from authorities to ensure safety, structure integrity, and fire compliance.
1. Appoint a Licensed Engineering Consultant
You must work with a Dubai Municipality (DM)–approved engineering consultant to:
Prepare layout plans
Perform structural calculations
Ensure design follows building codes and load standards
2. Documents Required
Trade License & Ejari (tenancy contract)
NOC from landlord/building owner
Architectural and structural layout
Structural load calculations
Fire safety layout (for Civil Defense)
Soil test report (for large-scale or industrial projects)
3. Submit to Relevant Authorities
Authority |
Purpose |
Dubai Municipality |
Structural and architectural approval |
Dubai Civil Defense |
Fire safety systems (alarms, sprinklers, etc.) |
Trakhees / Free Zones |
If property is located in JAFZA, DAFZA, etc. |
4. Review & Revisions
DM checks for compliance with load-bearing limits, safety, and accessibility
Civil Defense ensures adequate escape routes, fire resistance, and sprinkler coverage
You may need to revise drawings and resubmit
5. Fire Safety & MEP Coordination
Fire-rated materials and proper ventilation and lighting
Electrical, mechanical, and plumbing (MEP) layouts must be updated
6. Get Approval & Building Permit
Once everything is approved, DM issues a Building Permit for mezzanine construction. Civil Defense may issue a separate Fire Safety NOC.
7. Post-Construction Inspection
Submit as-built drawings
Final site inspection by DM and/or Civil Defense
Issuance of Completion Certificate
! Important Notes:
Mezzanine must not exceed 50% of the ground floor area unless otherwise approved
Ensure minimum height clearance (usually 2.2–2.4 meters above and below)
Use certified fire-rated materials and proper structural steel
Here’s a straightforward guide to obtaining Interior Design Approval in Dubai—essential for commercial and residential interior fit-out projects:
Interior Design Approval in Dubai
Whether you’re setting up an office, retail shop, restaurant, clinic, or salon, you must obtain approval for your interior design plans from the relevant Dubai authorities before starting work.
1. Hire a Dubai Municipality–Approved Consultant
You must work with a licensed interior design consultant or engineering firm who is registered with:
Dubai Municipality (DM)
Dubai Civil Defense (DCD) for fire safety compliance (if needed)
Free zone authorities like Trakhees, TECOM, DDA (if applicable)
2. Prepare Required Documents
Your consultant will prepare and submit:
Proposed interior layout plans (AutoCAD)
Reflected ceiling plan, electrical and lighting layout
HVAC, plumbing, and MEP drawings
Material specifications (especially for finishes and fire-rated items)
Trade license & Ejari
NOC from landlord or building management
Fire alarm and suppression layout (if required)
3. Submit to the Authorities
Depending on location and project type, submission is made through:
Dubai Municipality eServices Portal
Dubai Civil Defense Portal (for restaurants, clinics, warehouses)
Trakhees Portal (if in JAFZA, Nakheel, or other free zones)
4. Plan Review & Feedback
Authorities check for compliance with:
Dubai Building Code
Fire safety regulations
Space planning standards
Health and hygiene codes (for F&B or clinic)
Revisions may be requested and resubmitted by your consultant
5. Approval & Fit-Out Permit
Once approved:
A Fit-Out Permit is issued by Dubai Municipality or respective authority
You can now begin construction or installation
6. Final Inspection (if required)
For high-risk areas (kitchens, clinics, warehouses), inspections may be required before use
Completion Certificate or Final NOC may be issued after inspection
♦ Pro Tips:
Use DM-approved consultants to avoid delays
Follow Green Building Guidelines where applicable
Ensure your materials meet fire safety standards
Here’s a comprehensive guide to getting warehouse modification approval in Dubai, essential for businesses planning to alter, expand, or repurpose warehouse spaces.
Warehouse Modification Approval in Dubai
If you're modifying an existing warehouse—adding offices, mezzanines, partitions, HVAC, or changing usage—you must get formal approval from Dubai authorities before starting any work.
1. Hire a DM-Approved Engineering Consultant
You must appoint a Dubai Municipality (DM)-licensed consultant to:
Prepare modification plans (architectural, structural, and MEP)
Handle submissions to DM and Civil Defense
Ensure compliance with all building codes
2. Key Documents Required
Trade license & Ejari (tenancy contract)
Existing layout and proposed modifications
Structural calculations (for mezzanine or load-bearing changes)
Fire safety layout (for Dubai Civil Defense)
NOC from landlord/building owner
Photos of current condition
3. Submit to Relevant Authorities
Authority |
Purpose |
Dubai Municipality |
Structural, architectural, and space layout |
Dubai Civil Defense |
Fire safety systems and egress compliance |
Trakhees / Free Zones |
If located in areas like JAFZA, DAFZA, etc. |
4. Fire Safety Compliance
Fire alarm system, emergency lights, exit signage, sprinklers must meet DCD standards
Must appoint a DCD-approved fire contractor for design and execution
5. Get Fit-Out / Modification Permit
Once drawings are approved, you’ll receive a modification permit allowing legal execution of the project.
6. Site Work & Final Inspection
Execute work as per approved plan
Request final inspection by DM or Civil Defense (if required)
Obtain Completion Certificate or NOC for final clearance
♦ Important Notes:
Unauthorized modifications can lead to fines or disconnection of utilities
Mezzanine and HVAC works require special approvals
Warehouses used for hazardous materials have extra DCD requirements
Here’s a complete guide to getting villa extension approval in Dubai, whether you're adding a room, majlis, extra floor, or simply modifying existing structures:
Villa Extension Approval in Dubai
Extending your villa—horizontally (like adding rooms or garages) or vertically (an extra floor or roof structure)—requires official approval from Dubai Municipality (DM) /DDA/EMAAR/NAKHEEL and other concerned authorities to ensure structural safety, zoning compliance, and aesthetics.
1. Hire a DM-Approved Engineering Consultant
You must work with a Dubai Municipality–licensed consultant to:
Prepare updated architectural, structural, and MEP drawings
Submit and follow up on applications
Ensure all extensions meet Dubai building regulations
2. Required Documents
Title deed of the villa
Emirates ID of owner
Existing and proposed layout drawings
Structural calculations (if vertical extension)
Soil investigation report (for major structural changes)
NOC from developer or master community (e.g., Nakheel, Emaar, Dubai Holdings)
Photographs of current condition
MEP and fire safety layouts (if applicable)
3. Submit to Dubai Municipality
Your consultant submits documents through the DM e-Services Portal/DDA . Depending on location, additional submissions may go to:
Civil Defense (DCD) – for fire safety
DEWA / Etisalat / DU – for utility clearance
Free zone authorities (if applicable)
4. Review & Modifications
DM reviews the structural safety, zoning laws (like setbacks), and aesthetics
Revisions may be required—your consultant will handle this
5. Get Building Permit
Once approved, DM issues a Building Permit for the villa extension, valid for a specified time (usually 6–12 months).
6. Construction & Final Inspection
Execute the work using approved contractors
DM or relevant authority inspects the site upon completion
If compliant, a Completion Certificate is issued
♦ Tips for Smooth Approval
Ensure your extension does not exceed plot coverage limits
Respect community regulations (height limits, façade style)
Avoid starting any work before approval—penalties apply
Here’s a simple and clear guide to obtaining office partition approvals in Dubai, essential before modifying any commercial office space.
Office Partition Approvals in Dubai
If you're installing glass, gypsum, wooden, or aluminum partitions in an office space, you must get approval from the relevant Dubai authorities to ensure the layout complies with fire safety and building regulations.
1. Hire a DM-Approved Consultant
To begin, you need a Dubai Municipality–registered engineering or fit-out consultant who will:
Prepare the proposed layout with partitions
Ensure it complies with DM and Civil Defense requirements
Submit all documents and follow up on approvals
2. Required Documents
Valid Trade License & Ejari (tenancy contract)
Proposed partition layout drawings (AutoCAD format)
Existing layout (if applicable)
NOC from landlord/building management
Fire and life safety layout (if affecting emergency egress)
Consultant’s DM registration and license
3. Submit to Relevant Authorities
Your consultant will submit the documents to:
Dubai Municipality (DM) – for layout and structural clearance
Dubai Civil Defense (DCD) – for fire safety and escape route compliance
Free Zone Authorities (e.g., TECOM, Trakhees, DDA) – if the office is in a free zone
4. Authority Review & Comments
The authorities will check if partitions:
Allow proper egress (emergency exit)
Do not obstruct fire alarms or sprinklers
Comply with height, spacing, and ventilation requirements
Revisions may be requested if anything is non-compliant
5. Get Fit-Out Permit
Once approved, you’ll receive a Fit-Out Permit or Partition Permit, allowing the work to begin.
6. Execute Work & Final Compliance
Use certified materials (especially for glass partitions)
Maintain access to fire exits, signage, and lighting
In some cases, a final inspection or completion certificate may be required
♦ Pro Tips:
Don’t block sprinklers, smoke detectors, or emergency exits
For glass partitions, ensure tempered or laminated safety glass
In free zones, extra permissions from the zone developer may be required
Whether you’re opening a restaurant, clinic, warehouse, office, salon, or modifying an existing space, DCD approval is mandatory for any project that affects fire safety systems, occupancy, or internal layout.
1. Hire a DCD-Approved Consultant or Contractor
You must appoint a:
DCD-approved fire and safety consultant
Licensed fit-out contractor with DCD registration (for execution)
They prepare the fire safety layout and handle submissions.
2. Documents Required
Trade License & Ejari (tenancy contract)
NOC from landlord/building management
Proposed layout drawings (architectural, ceiling, HVAC)
Fire safety layout (sprinklers, alarms, extinguishers)
Material specifications (fire-rated walls, ceilings, doors)
Electrical load schedule and emergency lighting details
3. Online Submission to DCD Portal
Your consultant submits the documents via the Dubai Civil Defense e-Services Portal:
You must be registered on the portal
Each submission gets a reference ID for tracking
4. DCD Review & Comments
Civil Defense reviews:
Escape routes and emergency exits
Fire alarm & suppression systems (sprinklers, hose reels, detectors)
Material fire resistance ratings
HVAC system & smoke extraction (if applicable)
If any part doesn’t meet the code, DCD will request revisions
5. DCD Approval / NOC Issued
Once approved:
You receive a Fire Safety NOC for fit-out/modification
You can begin installation or construction
6. Site Execution & Fire Contractor Work
Install fire systems as per approved drawings
A DCD-certified fire contractor must carry out fire system works
Maintain access to all emergency exits and firefighting equipment
7. Final Inspection by DCD
After completion, request a Final Civil Defense Inspection
Inspectors verify installation matches approved plans
If passed, a Completion Certificate / Final NOC is issued
♦ Notes & Tips:
DCD approval is mandatory for high-risk spaces like restaurants, warehouses, kitchens, clinics, gyms, salons
Never start work without official DCD NOC—fines or shutdowns may apply
Use only DCD-approved materials and fire-rated systems
Here’s a step-by-step guide for getting salon approval from Dubai Municipality (DM) — essential for anyone opening a ladies’ or gents’ salon in Dubai:
Salon Approval from Dubai Municipality – Step-by-Step Guide
Opening a salon in Dubai requires several government approvals, including layout approvals, hygiene standards compliance, and health & safety certifications. Here's how to get started:
1. Choose an Approved Location
The salon must be in a commercial zone approved for salon activity
Obtain a tenancy contract (Ejari)
Check that the shop layout suits DM’s minimum space requirements:
Ladies' Salon: Minimum 3m x 3m per service area
Gents' Salon: Minimum 2.5m x 2.5m per station
Waiting area and separate stations for services (hair, manicure, etc.)
2. Trade Name & License (via DED)
Reserve a salon trade name through the Department of Economic Development (DED)
Business activity examples:
Ladies’ Beauty Salon
Men’s Barber Shop
Obtain an Initial Approval Certificate
3. Hire a DM-Approved Consultant
A licensed consultant will:
Prepare layout drawings of your salon (architectural + MEP)
Ensure compliance with Dubai Municipality's Health & Safety Code
Handle the submission through the Dubai Municipality e-Permit system
4. Required Documents
Trade license application
Ejari (tenancy contract)
Passport/Emirates ID of owner
Proposed layout plan showing:
Service areas
Water heaters in each treatment room
Ventilation and lighting
Separate areas for hair, face, and manicure/pedicure
Waste disposal and sanitation
5. Review by Public Health & Safety Dept. (DM)
Dubai Municipality checks for:
Minimum space per service
Water supply (hot & cold), sterilization units
Ceiling height (minimum 2.3 meters)
Flooring & wall finishes (washable and non-absorbent)
Proper ventilation and lighting
6. DM Health & Safety Approval
If all criteria are met, DM grants approval of the layout, and you can proceed to obtain the final trade license from DED.
7. Final DM Inspection (Post Fit-Out)
After fit-out, request a final DM site inspection
If compliant, a Health & Safety Certificate is issued, and you can legally open your salon
♦ Key Tips:
Use only approved salon furniture and equipment
Install sterilizers, covered waste bins, hair traps in wash basins
Maintain separate stations for each service
Never operate without full approval — violations may result in fines or closure
Here’s a detailed, easy-to-follow guide for obtaining restaurant and café approvals in Dubai, covering all the essential steps and authority requirements:
Restaurant & Café Approvals in Dubai – Complete Guide
Opening a restaurant or café in Dubai involves multiple approvals to ensure compliance with food safety, health, fire, and structural regulations. Here's how to get started:
1. Initial Trade Name & Business Activity Approval (DED)
Reserve your trade name with the Department of Economic Development (DED)
Choose the correct business activity (e.g., “Restaurant,” “Cafeteria,” or “Coffee Shop”)
Obtain your Initial Approval Certificate
2. Select a DM-Compliant Location
Ensure the premises meet Dubai Municipality Food Code requirements:
Minimum size: typically 250 sq ft or more, depending on concept
Adequate water supply, drainage, ventilation
Food preparation & storage areas
Separation between cooking and dining areas
3. Required Approvals & Documents
You'll need to coordinate with several departments:
Authority |
Purpose |
Dubai Municipality (DM) |
Health, food safety, interior layout approval |
Dubai Civil Defense (DCD) |
Fire safety NOC and final inspection |
Dubai Electricity & Water Authority (DEWA) |
Utility connection and load approval |
Free Zone Authority (if applicable) |
If located in DAFZA, TECOM, JAFZA, etc. |
Documents Required:
Tenancy contract (Ejari)
Trade name reservation & initial approval (DED)
Proposed layout drawings (prepared by a DM-approved consultant)
Kitchen ventilation, grease trap, and drainage layout
Fire safety system drawings
HACCP plan (for central kitchens or cloud kitchens)
4. Submit Layout for DM Approval
A Dubai Municipality–approved consultant will prepare and submit:
Architectural layout
Kitchen design & equipment layout
HVAC and fire safety system
Garbage area and storage zones
DM checks compliance with:
Dubai Food Code
Health and hygiene standards
Proper waste management and ventilation
5. Dubai Civil Defense (DCD) Fire Safety Approval
Submit fire alarm, suppression, and emergency layout
Install sprinklers, smoke detectors, emergency lights, and exit signage
Get fit-out NOC and schedule final inspection
6. Execute Fit-Out & Final Inspections
Work must be carried out by licensed contractors
DM and DCD inspectors will check the site post-completion
If compliant, you’ll receive:
DM Food Establishment License
DCD Final Approval/NOC
7. Final Trade License Issuance (DED)
After approvals, submit documents to DED for final restaurant license
You are now legally permitted to operate
♦ Pro Tips:
Include grease traps and stainless steel surfaces in kitchen design
Separate washbasins for hands and utensils
Storage must be off the floor
Never open before receiving all final approvals—hefty fines may apply
Here’s a step-by-step guide for obtaining retail shop fit-out approvals in Dubai, whether you're opening a fashion outlet, electronics store, supermarket, or boutique:
Retail Shop Fit-Out Approval in Dubai – Step-by-Step Guide
Before starting any interior work in a retail space, you must get approval from Dubai authorities to ensure safety, zoning, and design compliance. Here's how the process works:
1. Appoint a DM-Approved Consultant
You must hire a Dubai Municipality (DM)-approved engineering consultant or interior designer to:
Prepare architectural, electrical, and mechanical layouts
Ensure compliance with building regulations
Submit your application to relevant authorities
2. Documents Required
Trade license application or copy (from DED or Free Zone)
Ejari (tenancy contract)
Proposed fit-out drawings (AutoCAD)
NOC from building owner or mall management
Fire safety layout (if applicable)
DEWA load schedule (for lighting, A/C, equipment)
Materials list (especially for fire-rated items)
3. Submit Drawings for Approval
Your consultant will submit the design package to the following authorities based on your shop location:
Authority |
Scope |
Dubai Municipality (DM) |
Layout, electrical, plumbing, aesthetics |
Dubai Civil Defense (DCD) |
Fire & life safety compliance (if needed) |
Mall Developer / Landlord |
In-house approval before authority submission |
Free Zone Authority (if inside zones like DDA, Trakhees) |
Zone-specific fit-out approvals |
4. Review & Revisions
Authorities will review your fit-out plan for:
Safety (exit routes, fire systems)
Proper lighting, ventilation, and power capacity
Appropriate materials and finishing (non-combustible ceilings, etc.)
5. Receive Fit-Out Permit
Once approved, a Fit-Out Work Permit is issued by the respective authority (DM or free zone authority), which allows you to start physical work.
6. Execution & Compliance
Execute work using approved contractors
Follow the approved layout exactly
Ensure fire systems are installed and tested (if required)
7. Final Inspection (if applicable)
Upon completion, request a final inspection by DM or DCD
If all is compliant, you’ll receive a Completion Certificate / NOC
Then, you can legally open the retail store to the public
♦ Pro Tips:
Do not modify structure (walls, slabs) without structural approval
Follow mall or developer guidelines (if inside a shopping mall)
Never start work without a valid permit—fines and delays are common
Here’s a detailed, step-by-step guide to obtaining clinic or medical center authority approvals in Dubai, a process that involves multiple regulatory bodies including the Dubai Health Authority (DHA) and Dubai Municipality (DM).
Clinic / Medical Center Authority Approval – Dubai Guide
Setting up a clinic, dental center, physiotherapy facility, or diagnostic lab in Dubai requires strict approvals to ensure compliance with health, safety, and building codes.
1. Determine Business Activity & Location
Select the correct medical activity license (General Clinic, Dental Clinic, Dermatology Center, etc.)
Premises must be in a commercial or healthcare-zoned area
Minimum space requirements must be met (varies by specialty)
2. Initial Trade License Approval (DED or Free Zone)
Apply for a professional license via Department of Economic Development (DED) or relevant Free Zone Authority
Choose business activity like:
“Polyclinic”
“Medical Laboratory”
“Physiotherapy Center”
3. Hire a DHA-Approved Consultant
A DHA-licensed consultant or medical planner will:
Design your clinic according to DHA healthcare facility guidelines
Prepare architectural, mechanical, and electrical drawings
Submit your initial healthcare application to DHA
4. Submit Documents to DHA
Documents typically required:
Passport/Emirates ID of owner
Trade name reservation & initial license approval
Lease agreement (Ejari)
Proposed layout with departments (reception, consultation, sterilization, storage)
Site location map and building completion certificate
Fire safety plan (if clinic includes radiology or specialized labs)
5. DHA Initial Approval
If documents and layout meet DHA guidelines:
You’ll receive an Initial DHA Facility License Approval
You can now proceed with fit-out work
6. Dubai Municipality & Civil Defense Approvals
Submit your plans to:
Dubai Municipality (DM) – for layout, plumbing, waste, and MEP approval
Dubai Civil Defense (DCD) – for fire & life safety
DEWA – for load and utility approvals
7. Fit-Out Execution
Work must be carried out by a DM-approved contractor
Install medical equipment, sterilization units, washbasins, signage
Maintain infection control and patient safety standards
8. Final DHA Inspection
Once fit-out is complete:
Book a final DHA inspection
Inspectors verify:
Room sizes, ventilation, hygiene compliance
Staff areas, patient flow, sterilization systems
If compliant, DHA issues your Final Facility License
♦ Key Tips:
Provide one washbasin per treatment room
All surfaces must be non-porous and easily cleanable
Keep separate entrances for staff and patients where possible
Install sharps containers, waste management system, and fire alarms
Here's a comprehensive guide on getting Trakhees approval for warehouses in Dubai, particularly relevant if your warehouse is located in JAFZA, Nakheel, or other areas under Trakhees jurisdiction (Ports, Customs, and Free Zone Corporation).
Trakhees Approval for Warehouses – Step-by-Step Guide
Trakhees is the regulatory arm of PCFC (Ports, Customs and Free Zone Corporation) and governs construction, safety, and environment standards for developments in specific Dubai areas. Approval is mandatory for any new warehouse construction, modification, mezzanine addition, or change of use within Trakhees-controlled zones.
1. Determine if Your Warehouse Falls Under Trakhees
Check your location:
Trakhees regulates areas like:
JAFZA (Jebel Ali Free Zone)
Dragon Mart
Ibn Battuta area
Nakheel developments (International City, Palm Jumeirah, etc.)
If your warehouse is in these zones, Trakhees approval is required.
2. Appoint a Trakhees-Registered Consultant
Only a Trakhees-licensed engineering consultant can:
Prepare your architectural, structural, and MEP drawings
Ensure compliance with Trakhees Building Regulations & EHS standards
Handle online submissions via Trakhees e-permit system
3. Required Documents
Trade license (with warehouse activity)
Land lease agreement / Ejari
Existing warehouse layout (if modifying)
Proposed layout drawings:
Architectural
Structural (for mezzanine or heavy racking)
Electrical & Mechanical
Fire protection systems
NOC from Nakheel/JAFZA (if applicable)
Load calculation and DEWA approval (if electrical changes)
4. Submit Drawings to Trakhees
Your consultant uploads drawings to Trakhees e-permit portal, and it’s reviewed by departments like:
Civil Engineering
Environment, Health & Safety (EHS)
Fire & Life Safety
5. Review & Comments
Trakhees may return drawings for correction if:
Escape routes are unclear
Mezzanine exceeds loading limits
Materials are not fire-rated
Improper ventilation or drainage is shown
6. Trakhees Approval / Permit Issued
Once the drawings meet all codes:
You receive a Construction Permit or Modification Approval
You can begin work under supervision of the registered consultant/contractor
7. Fit-Out or Construction Execution
Work must be done by a Trakhees-approved contractor
Fire systems, mezzanine structures, and insulation must match approved plans
EHS inspections may occur during the build phase
8. Final Inspection & Completion Certificate
After construction:
Schedule a Final Inspection with Trakhees
EHS, Civil, and Fire departments will assess compliance
If all checks pass, a Completion Certificate / NOC is issued
♦ Pro Tips:
For mezzanine additions, structural load calculations are strictly reviewed
Ensure smoke detection, fire alarms, and extinguishers are included in designs
Maintain minimum aisle widths and emergency exit access
Violations can result in delays, fines, or rejections
Office : 501,
Al Rahaf Tower
Al Qusais Industrial Area 4,
Post Box : 35361- Dubai
© approvals.ae. All Rights Reserved.